New Maryland Transmission Line Would Disrupt Hundreds of Acres of Forests and Wetlands, CBF Report Finds

Piedmont Reliability Project Must Properly Mitigate Threats to Habitat and Water Quality

Over 500 acres of protected land, including vulnerable forests and high-quality watersheds, would be threatened by the Maryland Piedmont Reliability Project, according to a new analysis by the Chesapeake Bay Foundation (CBF). In the fight for cleaner water across the Chesapeake Bay watershed, CBF today issued new geospatial data regarding how the controversial proposed transmission lines in Baltimore, Carroll, and Frederick Counties would harm wetlands, forests, and habitat.

“If done thoughtlessly, this project would be a huge backslide on Maryland’s robust environmental investments,” said Gussie Maguire, CBF Maryland Staff Scientist. “But we are not powerless. Maryland can and must enforce strict regulations to minimize and mitigate the environmental losses from this project, and ensure support for affected communities.”

Data summary

According to CBF’s Geographic Information System (GIS) findings, the transmission line’s right-of-way will cut through: 

  • 514 acres of protected area, including Maryland agricultural preservation foundation easements (a vast majority at 374 acres), Forest Conservation Act acres, and a portion of Gunpowder Falls State Park; 
  • 483 acres of Tier II watershed—a classification of high-quality watershed acres that represent the cleanest water and most valuable habitat in Maryland;
  • 377 acres of forest cover, which filter carbon from the atmosphere and keep streams cool in the face of climate change;  
  • 47 acres of wetlands, which prevent pollution by soaking up excess nutrients and provide quality habitat; and,
  • 125 acres of riparian buffer, or vegetation surrounding streams and water bodies that improves water quality and environmental benefits.

CBF’s GIS survey data was derived from information released by the project developer, utility company Public Service Enterprise Group, Inc (PSEG), and assumes a 150-foot-wide easement around the length of the transmission line.

Background

In October, PSEG announced a proposed route for the Maryland Piedmont Reliability Project, which the company said would deprioritize environmental concerns. All three counties where the line will intercede—Baltimore, Carroll, and Frederick—have fiercely opposed the project.

Maryland’s electric grid operator, PJM, asserts that a high-powered transmission line is necessary due to the growing demand for power from data centers in Northern Virginia. The proposed 500,000-volt transmission line’s area of impact would be roughly 70 miles long and 550 feet wide.

PSEG still needs to submit a permit application to the Maryland Public Service Commission (PSC) before the project can proceed. That application is expected before the end of 2024.

Why It Matters

If classified as necessary utility infrastructure, this project would be exempt from Maryland’s Forest Conservation Act, including conservation and reforestation requirements. However, PSC’s permit could include additional conditions that effectively minimize the line’s environmental harm wherever possible and enforce mitigation requirements where avoidance is not possible.

This is the first of 10 transmission lines that PSEG intends to construct through Maryland. It is paramount that PSC sets a strong precedent with this initial permit, enforcing the highest environmental standards and ensuring maximum remediation for affected communities. 

As the state moves towards a greener grid and electrification of appliances and cars, more power will be needed. However, the deforestation and environmental devastation required would contradict many of Maryland’s climate change goals. It is much more cost-effective to preserve high-quality waterways upfront than to try and restore streams and landscapes after devastation occurs.

Preserved forests and wetlands in the upper reaches of the Chesapeake Bay watershed are some of the most effective water filtration systems and fighters of climate change. They provide habitat for many of Maryland’s most beloved wildlife species who are already experiencing forest fragmentation and habitat loss from intense development pressure.

Residents voiced their concerns last week during a series of public hearings in Baltimore, Carroll, and Frederick Counties. CBF encourages concerned advocates to email questions and comments directly to the Maryland PSC inbox at [email protected]

valerie-keefer_90x110.jpg

Valerie Keefer

Maryland Communications & Media Relations Manager, CBF

[email protected]
443-482-2023

The Bay Needs You

The State of the Bay Report makes it clear that the Bay needs our support now more than ever. Your donation helps the Chesapeake Bay Foundation maintain our momentum toward a restored Bay, rivers, and streams for today and generations to come.

Donate Today

Save the Bay

Founded in 1967, the Chesapeake Bay Foundation (CBF) is the largest independent conservation organization dedicated solely to saving the Bay.

Save the Bay
x
This website uses cookies to tailor and enhance your online experience. By continuing, you are agreeing to our use of cookies. For more information, including details on how to disable cookies, please visit our Privacy Policy. Close